Billerud Reverses Decision on Escanaba Mill


Despite the State of Michigan's commitment to support the mill upgrades with a $200 million investment, Billerud has cancelled plans to move forward with a $1 billion conversion of its mill in Escanaba, MI. The giant mill employs roughly 860 workers and the conversion/upgrade was expected to add more than 1000 jobs during construction. Currently the Escanaba plant produces graphic papers with three machines in operation. However, the past nearly 2 years of planning and engineering were to bring to fruition a substantial conversion of the mill to produce cartonboard. The project would have been the largest ever investment in the Upper Peninsula. The Escanaba mill is the largest manufacturing employer of full-time workers in the region. Billerud President and CEO Ivar Vatne said feasibility studies showed the projected return on investment would not be sufficient to enable the company to proceed with the mill modifications and conversion.